A digital illustration of offshore wind turbines, power lines, and the text 'RWE Reflections' against a blue background.
STA02-reflections

Lack of grid infrastructure is the single biggest blocker to deployment of new low carbon power.

Reforming the Offshore Transmission Regime


A person stands confidently with arms crossed, wearing a bright red dress in a modern office space with natural light.
TIC02-nicola-crawford-percival

Nicola Crawford-Percival, Head of Regulatory Affairs UK & Ireland RWE Renewables UK


The UK's ambitious offshore wind targets demand significant investment in electricity transmission networks and regulatory reform.

Currently, the primary hurdle to deploying most new low-carbon power is the lack of adequate grid infrastructure. But while the onshore transmission network has rightly received considerable attention in recent years as it looks to tackle the problems, offshore networks connecting wind farms out at sea to the grid on land, have arguably been less in the spotlight.

Reforms to the offshore transmission regime are urgently needed to deliver the existing pipeline of projects most effectively, and ensure that such delivery is ultimately achieved at least cost for consumers and developers. 


Current offshore transmission management

In the 1980s, the British electricity market was liberalised, separating generation, transmission, distribution and supply into distinct, licensable activities. Onshore transmission is managed by three Transmission Owners (TOs), each a regulated monopoly covering discrete parts of GB. However, the Offshore Transmission Owner (OFTO) regime sees developers build and then transfer transmission assets to OFTOs, which will then operate and maintain them. Ofgem manages the tender process for this transfer. This system, initially designed for smaller and less complex projects, now faces significant challenges as the offshore wind sector continues to grow as the backbone of our energy system.


Key issues in the OFTO regime

A blue exclamation mark symbol above a circular dot on a black background, indicating emphasis or warning.
TIC02-imbalance-of-risk

Imbalance of risk:

The OFTO regime has evolved into a complex financial structure, where developers retain significant liabilities even after selling assets. OFTOs can exploit this by making uncommercial demands, knowing developers face tight deadlines and potentially severe penalties under the Generator Commissioning Clause.

Navy graphic shows a round circle with blue pound sign in the middle
TIC02-geldstueck

Cost-assessment flaws:

The regime aims to provide consumer value and ensure timely infrastructure delivery. However, changes in the market, such as the introduction of Contracts for Difference (CfDs), have made Ofgem’s cost assessments less relevant and often unfairly burdensome for developers.

An illustration featuring a wrench alongside a power transmission tower, symbolising tools and energy infrastructure.
TIC02-maintenance-and-repairs

Maintenance and repairs:

Offshore wind projects are wholly reliant on the OFTO assets to which they connect for a route to market, with severe financial consequences for the generating station if market access is not available. OFTOs are thinly capitalised and often with limited insurance. This therefore incentivises OFTOs to operate a less stringent maintenance regime for their offshore transmission assets (e.g. cables and substation) than offshore wind generators tend to undertake for their assets offshore (e.g. cables linking the turbines). The evaluation criteria for OFTOs qualifying to tender for assets prioritises price over the capability to maintain assets effectively.

A blue light bulb icon with rays emanating from its base, symbolising illumination and energy.
TIC02-gluehbirne

Life-extension and decommissioning:

There is a lack of clear policies on life extension and decommissioning of OFTO assets. With many offshore wind farms nearing the end of their agreements by the early 2030s, urgent policy development is needed to prevent unnecessarily early decommissioning.


Impact and required changes

These issues create inefficiencies and additional costs, which ultimately affect consumer prices. To address these problems, RWE suggests two main changes:

  1. Radial transmission assets:

    Allow generators to retain ownership of newly built assets and reclaim legacy assets after the OFTO revenue term. This will reduce conflicts of interest and incentivises cost-effective, efficient transmission asset management.

  2. Shared grid development:

    Revise the regime to make third-party grid building commercially viable; and ensure financial robustness of third-party owner-operators and appropriate compensation to generators for delays, learning from other European countries.

Conclusion

The UK's offshore wind sector has grown significantly, but maintaining this leadership requires immediate action to reform the OFTO regime. Effective reforms will ensure the offshore transmission network can support future growth efficiently and cost-effectively.



You might also be interested in

Driving the energy transition and delivering for farmers and nature

Solar is playing a key role in helping decarbonise the UK ‘s power system and securing the nation’s energy supplies.

Read more

A call for strategic renewables investment and policy realignment

RWE outlines why we need to change and how, if we’re to secure a bumper yield of offshore wind in AR6 and maximum “bang for your buck” for consumers.

Read more

Removing the barriers to low carbon power

Solving the grid connection challenge: practical solutions to accelerate progress. By Tom Glover, RWE UK Country Chair

Read more